26 May 2014

Getting the Ideas from the team and building a solution - Nominal Group Technique (NGT)

The nominal group technique is used to generate ideas from team in Problem identification, solution generation and decision making. It can be used for teams of any size but ideally limited between 5 to 9 members. This number is ideal to get diversity and easy to find consensus among the team. This technique is particular useful when few of the team members are more vocal than others. Generally a facilitator leads the team and manages the interaction. the steps are below.
  • The Facilitator introduces the team and presents the problem to the team after explaining the purpose and procedure during the meeting
  • All the team members are advised to create their ideas silently and individually on a sheet of paper. No consultation or discussion allowed
  • The Facilitator then requests and records all the ideas from all the members in a sequential manner till all the ideas are exhausted. ( No discussion is allowed till all the ideas are exhausted). This will allow all the team members to present their ideas.
  • Building on the existing ideas is permitted during the presentation
  • The ideas are then evaluated and discussed among the team. Duplicate ideas are eliminated or merged with the team consensus. Seeking additional information from the idea generator is allowed. Facilitator ensures that focus is not concentrated on single or very few ideas.
  • Voting for the best solution is then conducted to get the group consensus using the multi voting in the following way.
  • All the members rank the final list of ideas according to their choice silently.
  • The total votes are tallied and ideas with lowest votes are eliminated. This process can be repeated till optimum solution is generated.

One of the main advantages is that the team gets equal chance to participate and also force the silent participants to be active. Second major advantage is that this method generates more ideas than a interactive session.

24 May 2014

Metrics Used in Six Sigma

The Most commonly Used metrics in Six Sigma are as below. First let us list the symbols

 

Total Number of Defects – D

Number of Units – U

Number of Defect Opportunities per Unit – O

Yield = Y

First Time Yield = FTY

Rolled Throughput Yield = RTY

Probability of Defect = P (d)

 

Total Opportunities (TOP) = clip_image002[9] 

 

Defects per Unit (DPU) = clip_image004[7]

Defects per unit opportunity (DPO) = clip_image006[7] =

                                                                      clip_image008[4]

                                                               

Defects per Million Opportunities = clip_image010[7]

 

First time Yield = clip_image012[7]

Rolled Throughput Yield = clip_image014[7]

Probability of Defect = 1- FTY

08 October 2013

Key Components of a Project Charter I – Problem Statement

image_thumb[11]

For having a Clear and Very good Project Charter, the following Components are very important. A clear understanding of the problem will help not only to build the business case to be presented, but also quickly arrive at solutions. A Problem well understood by all the stakeholders is half resolved.

The Key components of a charter are

· A Clear and un ambiguous Problem Statement.

· A Clearly defined and reachable goal to resolve or in the direction to resolve the problem

· A Business Case, stating the benefits which can be achieved by resolving the problem.

Let us first discuss the Problem Statement. It is a Known proverb that if understand the problem clearly, you are half way to the solution. A Good problem Statement shall address the following.

What?

· What is the process that is involved?

· What is wrong?

· What is the gap / opportunity?

Where/When?

· Where do we observe the problem / gap?

· What is the period for which we looking at?

· When do we observe the problem / gap?

How big?

· How big is the problem /gap/opportunity?

· What are the parameters it is impacting and by how much

· How will we measure it?

Impact? (Importance)

· What is the impact of the problem /opportunity?

· What are the benefits of the action /consequences of inaction?

Problem Statement – Example

For the period from Jan 2013 to Jun 2013 (When), the Average Fuel Consumption (What) of all the Luxury service buses is at 4.3 KMPl against a target of 6 KMPL (magnitude). This has resulted in a loss of 700000INR (Impact).

Key Considerations / Potential Pitfalls

· Is the problem based on facts or assumptions?

· Is data available or can be collected to verify and analyze the problem?

Potential Pitfalls

· Is a solution included or implied in the statement?

· Would customers be happy if they knew we were working on this?

· Does the problem statement prejudge a root cause?

· Is the problem statement too narrowly or broadly defined?

Please share this on Facebook. if you like this blog, like us on our Page

29 September 2013

What is Design of Experiments (DOE)

Designed of Experiments (DOE) is a structured approach for varying process and/or product factors (x’s) and quantifying their effects on process outputs (y’s), so that those outputs can be controlled to optimal levels. 

DOE deals with identification of critical factors and their reponse variables, and the magnitude of the response for each level of each of the critical factors. DoE is also used to understand the interaction between the various critical factors to ensure right mix of the critical factors to obtain the optimum amount of response.
DoE is used to understand the transfer function and mathematical model for the optimization of the response variable.
DC motor manufacturer might wish to understand the effects of two process variables, wire tension and trickle resin volume, on motor life. In this case, a simple two factor (wire tension and trickle resin volume), two level (low and high values established for each of the two factors) experiment would be a good starting point. Randomizing the order of trials in an experiment can help prevent false conclusions when other significant variables, not known to the experimenter, affect the results. There are a number of statistical tools available for planning and analyzing designed experiments.

17 September 2013

What is a Project Charter in a Six Sigma Project - What are the main elements of the Charter

A Project Charter is essentially a planning doument for the six sigma project. The document also serves as an acceptance document for the project. This is the essential record through which the management accepts and supports the project. This document is essentially an agreement between the Management and the project team on what is expected from both the sides. This is used to 
  • Keep the project team aligned with the organizational Goals.
  • Clarifies what is expected out of the team
  • Keeps the team focussed on the objective
  • the project teams role is in fact increased from the champion after the charter is agreed.

A charter is prepared, once you have defined the problem, to communicate and confirm agreement between the problem-solving team and management. A simple template is presented here. http://www.docstoc.com/docs/147469086/Six-Sigma-Project-Charter-Template?

There can be many other forms to use for a project charter. The most important information needed for management to approve the project must be captured here.

Here are the essential elements of the Project Charter
  • Project Name
  • Project Goal
  • Problem Statement
  • Business Case
  • Milestones
  • Support Needed
  • Estimated Cost
  • Signatures/Approvals.
These will define the complete description of the project in the language fo Management.

11 August 2013

Key Components of a Project Charter II

image  In the previous sections I have covered the list of key components and the problem statement in the following articles. I will continue this discussion on the Charter so that the problem is well understood at all levels and support wherever needed in clearly identified. A good start is half done. Same way in a Six sigma Project, A good charter becomes heart of the project and to achieve the goals.
http://www.excellencementor.net/2013/09/what-is-project-charter-in-six-sigma.html
http://www.excellencementor.net/2013/10/key-components-of-project-charter-i.html
Once you have defined the problem clearly the other sections of the charter need to be completed.  Follow these sections in the order so that the logical flow is available. However, this is not mandatory. The details are below.
Project Goal or Goal Statement: The Goal statement is linked to resolution of the problem. Important consideration here is to set a goal which is achievable in a period of about 120 to160 days. The goal is agreed by the team and team champion as achievable. This really helps in setting the scope of the project.
Business Case & Estimated cost: This section is for the Management to understand the Return on Investment. This shall be as realistic as possible since this is commitment to the Management on the benefits of the project. The business case shall be linked to resolving the problem and the benefit shall be in line with reducing the losses as outlined in the problem statement and achieving the goal in the goal statement.
Support Needed: This will help the management to understand allocation of resources and support. This shall outline the likely support needed from outside the project team.
Milestones: Clearly define the timelines for each of the phase of the project. This will help to see if the project is in the right direction and correct course by both management and the project team.
Signatures/Approvals : This is just a commitment for the project both from management and the project team.

 